HomeIndiaRailways links two sides of 6.59 km tunnel on Rishikesh–Karnaprayag route

Railways links two sides of 6.59 km tunnel on Rishikesh–Karnaprayag route

Published on

3 min read

November 27, 2026 — Indian Railways said on Friday that crews had connected the two excavated sections of the 6.59-kilometre Tunnel 14 on the Rishikesh–Karnaprayag railway project in Uttarakhand. The breakthrough took place in Rudraprayag district, where crews worked from the Sumerpur and Marora portals.

File photo: the rivers at Devprayag, Uttarakhand, May 26, 2011. Anubha khare / Wikimedia Commons, CC BY-SA 4.0.

Key highlights

  • The tunnel’s two excavation approaches met on November 27.
  • The Ministry of Railways reported a 4.7-kilometre drive from Sumerpur and 1.79 kilometres from Marora.
  • The work included excavation beneath inhabited areas and work to stabilise ground near Marora.

What the breakthrough means

A tunnel breakthrough is the point at which excavation fronts meet. On this project, it links the works driven from the two portals and marks progress on one part of the Rishikesh–Karnaprayag route. The Ministry of Railways announced an excavation milestone and did not announce the start of passenger services.

Rail Vikas Nigam Limited carried out the work, The Indian Express reported. Construction teams faced different conditions at the two ends. Sumerpur included a stretch beneath inhabited areas, while Marora required work to stabilise the slope and address settlement issues before the main drive.

Construction conditions at the two portals

The ministry said a 110-metre stretch near Sumerpur ran through loose soil beneath inhabited areas. It reported a cover of about 20 to 30 metres over the work there. Crews used specialised excavation methods to work in those conditions.

At Marora, the ministry described work to secure the slope and address settlement and acquisition issues. It said the main drive at that end started in March 2024. The two approaches illustrate why progress can vary considerably between sections of the same tunnel.

What the project is intended to serve

The railway ministry describes the wider project as a way to improve access to Uttarakhand’s hill regions for residents, pilgrims and other visitors. The benefits will depend on the eventual opening of the line and how train services connect with onward journeys.

An excavation breakthrough is followed by further civil and railway work. Track, operational systems and safety clearances are the kinds of milestones that matter before trains can run. Announcements on those steps will give passengers a firmer basis for planning than dates associated with excavation alone.

Location or milestoneMinistry’s description
Sumerpur portal4.7 km excavation approach
Marora portal1.79 km excavation approach
Tunnel 146.59 km, with the main excavation sections connected

Related coverage: India and Nepal’s Janakpur–Ayodhya weekly train plan.

What to watch

Look for updates on finishing work in Tunnel 14 and on readiness of connecting sections. Service schedules and bookings will become relevant after the railway announces commissioning and the operating plan.

Sources

Written by
National Desk

The National Desk covers India's politics, governance, security and public-interest news. Stories are checked against at least two credible sources before publication.

Latest News

Latest News

Singapore checks impact of US chip controls as Nvidia shipment halt stays unconfirmed

Deputy Prime Minister Gan Kim Yong said Singapore was consulting businesses and reviewing its processes as reports of a shipment halt remained unconfirmed.

Dutch prime minister to raise US chip-equipment bill with Trump at G20

Rob Jetten plans to discuss the proposed US MATCH Act at the Miami G20, where Dutch concerns about the effect on export controls to China will be on the agenda.

Taiwan lifts 2026 growth forecast to 13.28% as AI demand boosts exports

Taiwan lifted its 2026 GDP growth forecast to 13.28%, while a preliminary estimate put third-quarter growth at 14.39% year on year.

Kashi Tamil Sangamam to open in Varanasi with Thirukkural as its theme

The fifth Kashi Tamil Sangamam is scheduled for November 28 to December 12, with more than 1,400 delegates expected, the Ministry of Education said.

Related Coverage

India hands over three bronzes returned from the US and Netherlands to Tamil Nadu police

Three repatriated bronzes were handed to Tamil Nadu police in New Delhi, including two returned from the Smithsonian and one from the Netherlands.

India Post outlines ₹2,632 crore plan for operations and buildings

India Post’s ₹2,632 crore five-year outlay covers postal operations, parcel logistics and upgrades to customer-facing buildings.

Gadkari announces ₹75,000 crore in West Bengal highway projects

India’s road transport ministry outlined ₹75,000 crore in highway projects for West Bengal, including a proposed Kolkata ring road.