November 24, 2026 — Vietnam’s Thang Long Project Management Board has selected a consortium led by France’s Systra to prepare feasibility and engineering work for the North–South high-speed railway. The approved bid for the consultancy package exceeds 10.24 trillion dong. The board and consortium are due to negotiate before a formal contract is signed.
Key highlights
- The board announced its selection for consultancy package TV-02 on November 22.
- The eight-member consortium includes companies from France, Vietnam and South Korea.
- The package covers surveys, a feasibility study, front-end engineering and tender documents over 30 months.
- The planned line would run 1,541 kilometres between the Hanoi and Ho Chi Minh City areas.
What the consortium will prepare
The selection concerns the technical work that comes before construction. Consultants are expected to survey the route, assess engineering and investment options, and prepare tender documents. The feasibility report will give Vietnamese authorities a basis for considering the project’s investment decision.
France’s Systra leads the group. Vietnam News Agency identified three South Korean members, Sambo Engineering, Yooshin Engineering Corporation and Korea National Railway. Four Vietnamese firms complete the consortium, including TEDI and TEDI SOUTH.
How the project is structured
The route runs between Ngoc Hoi in Hanoi and Thu Thiem in Ho Chi Minh City under the proposed alignment. Vietnam News Agency reported that the line is designed for trains travelling at up to 350 kilometres per hour. That is a design specification. Operating speeds and travel times will depend on how the railway is built and run.
The 10.24 trillion dong figure describes the approved consultancy bid. The full railway is a much larger investment, with financing, land clearance, civil works and rolling stock involving decisions beyond this package. VnEconomy reported that the approved consultancy work has a 30-month duration.
Why contract negotiations matter
The selected team and the project board still have to agree the formal contract. Surveys and engineering studies can alter choices along the route. The resulting feasibility study and tender documents are meant to give later bidders and public authorities a common set of project specifications.
What to watch
Watch for formal signature, the start of survey work and publication of milestones for the feasibility study. The contractor selection advances project preparation. Construction packages and the funding for them remain separate decisions.