November 28, 2026 — The Philippines broke ground on November 27 for the Pambuhan offshore wind port in Mercedes, Camarines Norte. The Department of Energy says the first phase is being financed through the Philippine Ports Authority under a ₱2.27 billion contract. It expects the facility to be operational by early 2028.
File photo: Waterfront in Mercedes, Camarines Norte, uploaded June 23, 2009. The photo shows the municipality, where the new Pambuhan project is located. Ringer / Wikimedia Commons, CC BY-SA 3.0. Automatic site display crops.
Key highlights
- The Philippine Ports Authority is developing the facility with local and other partners.
- Phase one includes a 2.9-hectare area for port operations, berthing and staging.
- The energy department describes the broader project as a 40-hectare logistics hub.
What the first contract covers
The Philippine Ports Authority held the groundbreaking on Friday. The Philippine News Agency reported that the first phase includes a 2.9-hectare operational, berthing and staging area and a temporary access road of about 431 metres. Daily Tribune reported the same initial works and described the contract as about ₱2.3 billion, a rounded figure.
The Department of Energy says the broader port is planned over 40 hectares. That describes the wider facility, while the 2.9-hectare figure describes part of the first phase. The first announcement and the project’s larger footprint therefore refer to different scopes.
Why a dedicated port is part of the wind plan
Offshore wind projects rely on a place to receive and stage components such as turbine blades, towers and foundations. These components can be larger than the equipment handled by some conventional cargo facilities. A marshalling port gives developers and suppliers a place to organise them before they are moved offshore.
Pambuhan is an infrastructure project serving potential offshore generation. The groundbreaking itself establishes construction progress on the port. It does not make electricity available or guarantee the completion of any individual wind farm.
The wider energy targets
The Department of Energy identifies 14 registered offshore wind service contracts in areas near the port. A service contract indicates developer activity, while finance, permitted construction and eventual generation are later milestones. The department’s broader targets are for renewables to account for 35% of the power-generation mix by 2030 and 50% by 2040.
Port readiness will be one part of meeting those objectives. Wind projects also depend on project timelines and the capacity to bring electricity onto the grid. The relative timing of those investments will affect when the logistics facility starts serving operational projects.
| Project measure | Announced scope |
|---|---|
| First-phase contract | ₱2.27 billion |
| First-phase port operations and staging area | 2.9 hectares |
| Wider facility | 40 hectares planned |
| Target for port operations | Early 2028 |
Related coverage: Philippines posts record $6.95 billion goods trade deficit as imports jump.
What to watch
Watch first-phase construction and subsequent port works, and whether nearby wind proposals reach investment and construction milestones. Early 2028 is the department’s expected operating date.