Cabinet Approves ₹14,500-Crore Scheme for 92 GWh of Grid-Scale Energy Storage, With 40% Local Content for Batteries

Published on

3 min read

NEW DELHI, November 6: The Union Cabinet has approved a ₹14,500-crore Viability Gap Funding (VGF) scheme to support 92 gigawatt-hours (GWh) of new grid-scale energy storage, the government said on Wednesday. The scheme covers 60 GWh of pumped hydro storage, 30 GWh of battery storage and 2 GWh of newer technologies, and will run from 2026-27 to 2030-31.

Key highlights

  • Support: ₹14,500 crore in VGF for FY 2026-27 to FY 2030-31.
  • Capacity: 92 GWh in total: 60 GWh pumped storage, 30 GWh battery energy storage systems (BESS) and 2 GWh alternative technologies.
  • Investment: an estimated ₹97,600 crore in total.
  • Made in India: battery projects must meet a minimum 40% domestic content requirement.
  • Allocation: through tariff-based competitive bidding; distribution companies are eligible for support for BESS and pumped storage.
What the scheme supports
TechnologyCapacity supportedWho is eligible
Hydro pumped storage plants60 GWhPublic and private electricity distribution companies
Battery energy storage systems30 GWh (40% domestic content)Public and private electricity distribution companies
Alternative storage technologies2 GWhPublic and private sector entities
Total92 GWh—

Why storage matters

Solar and wind power vary through the day and the year. Storage lets the grid save surplus renewable power and use it in the evening or when the wind drops. The government said the scheme will add new capacity equal to 170% of India’s present grid-scale storage capacity and help meet the 411 GWh of grid-scale storage it says will be needed by 2031-32. It said the scheme would improve grid stability, cut reliance on conventional power for balancing, and boost domestic manufacturing of batteries.

Our calculation

  • The VGF of ₹14,500 crore covers about 15% of the estimated ₹97,600-crore investment; the rest must come from developers and lenders.
  • If 92 GWh equals 170% of present capacity, India’s current grid-scale storage is roughly 54 GWh.
  • Even after this scheme, about 265 GWh more would be needed to reach the 411 GWh target by 2031-32 (411 minus 54 minus 92).

What it means

Storage is the missing piece in India’s renewable energy plans: without it, extra solar power at midday is wasted and coal plants are still needed for evening peaks. The 40% domestic content rule is meant to build a battery industry at home and reduce imports, most of which come from China. Pumped hydro, which makes up two-thirds of the planned capacity, takes years to build, so progress will depend on quick bidding and project approvals.

What to watch

  • Scheme guidelines and the first bidding rounds.
  • Tariffs discovered in the auctions, which will show how cheap storage has become.

Tehri Dam in Uttarakhand, which hosts a pumped storage hydro plant. Image: Dr Vikramjit Kakati, CC BY-SA 4.0, via Wikimedia Commons. Photo source · Licence

Sources

Written by
Business Desk

The Business Desk covers markets, the economy, companies and personal finance. Stories are checked against at least two credible sources before publication.

Latest News

Latest News

India Wins Record 114 Medals at Asian Para Games 2026, Including 30 Golds and Five World Records

India won a record 114 medals at the Asian Para Games 2026 (30 gold, 35 silver, 49 bronze), with five world records. PM Modi met the contingent in New Delhi.

DRDO Successfully Tests Pralay Quasi-Ballistic Missile in User Trials; Induction ‘Imminent’

DRDO flight-tested the Pralay quasi-ballistic missile from Dr APJ Abdul Kalam Island on November 5 as part of user trials; the ministry said induction is imminent.

Cabinet Approves ₹2,814-Crore Scheme for Lithium and Nickel Processing Plants to Cut Import Dependence

The Cabinet approved a ₹2,814-crore scheme offering a 30% capital subsidy for two lithium and two nickel processing plants to reduce India’s import dependence.

Cabinet Opens Path for All Agniveers to Become Regular Soldiers: 25% Now, the Rest After a Second Two-Year Term

The Cabinet has created a pathway for all Agniveers to join the Defence Forces as regular soldiers: 25% on merit after four years and the rest after a second two-year term.

Related Coverage

Malabar 2026: INS Sahyadri Reaches Japan for Quad Navies’ Exercise as Indo-Pacific Dialogue Ends in Delhi

INS Sahyadri has reached Yokosuka, Japan, for Exercise Malabar 2026 with the navies of Japan, the US and Australia, as the Navy’s Indo-Pacific Regional Dialogue ended in Delhi.

Global Growth Slows to Three-Month Low in October; India and the US Lead, France and Australia Shrink

The J.P.Morgan Global Composite PMI fell to 53.2 in October from a 40-month high. India and the US grew strongly, while France, Australia and Canada contracted.

Japan’s Services Growth Edges Up to 51.7 but Hiring Slows to 14-Month Low as Prices Stay High

Japan’s services PMI rose to 51.7 in October, but hiring slowed and the composite index eased to 52.1. Price pressures remain sharp as the Bank of Japan weighs more tightening.